For this our first project down at the Ashdown College, ESH designed, supplied and installed two separate trace heating system to provide the following:

  • Frost protection to the cold water pipework in the first floor plantroom
  • To temperature maintain the DHWS pipework throughout two levels 

In total, this project saw ESH install over 1km of trace heating cable.