Monday, 30 July 2012

Worcester Boat House

A rowing boat house owned by Birmingham University, here we supplied and installed frost protection to the MCWS pipework on both the roof and ground floor area.

Friday, 20 July 2012

Stepan UK, Stalybridge

Supplied and installed a trace heating system to provide frost protection to 1" diameter emergency shower pipework.

Tuesday, 10 July 2012

Creswick Primary School, Welwyn Garden City

Within this new Primary School building, ESH provided a frost protection system to the sprinkler pipework in the unheated loft space. Over 350 metres of type ESRS self limiting heating tape was supplied and installed.

Monday, 9 July 2012

Holland Park School, London

Supplied and installed a trace heating system to frost protect the new chiller pipework and to splice the new system to the existing.

Tuesday, 3 July 2012

Northwick Park Hospital, Harrow

Here we were contracted to test the existing run of Raychem heating cable on redundant pipework. If it tested clear remove and install on the new chiller pipework.